8. Dangote Group brought in the world’s #1, #2, and #5 sand dredgers to sand fill the site. 60% of the land being swampy. So far these dredgers have reclaimed 13 million m³ out of 30 million m³
9. During construction, the project will employ over 25,000 Nigerians
10. When this project comes online, Nigeria will save a minimum of $10 billion a year on imports
11. The Ammonia component of the plant will produce 2.8 million tonnes of Urea
12. Dangote is producing its own electricity to power the plant and by so doing is saving 75% costs. Dangote produces electricity at a rate that is significantly cheaper than the Federal Government. Dangote’s cost is $400,000/MW, while Federal Government is $2,000,000/MW
13. All the civil engineering is done by Nigerian companies